Dan's RV7a Builder Website

Fuselage

Date Session Hours Task
2/1/2006 2 Route fuel lines to cabin valve
1/29/2006 6 Fuel vent lines, rudder attach fab from SS bar
1/12/2006 2 finish fuselage-flap holes, mount to acuator, test
3/15/2005 1 final rivet front cowl skin
2/1/2005 1 complete slider rail screw attachments, relocate sub panel terminal block
1/31/2005 1.5 continue riveting forward top cowl & support brace & sides
1/30/2005 2 rivet forward top skin onto fuselage
1/29/2005 4 rebuild & attach fuel vent lines, attach brake cables to master cylinder, cleco top skin in prep for final rivet
1/23/2005 1 complete fuel tank bracket setup
1/21/2005 1.5 fuel tank bracket setup
1/18/2005 0.5 remove fuel vent line for rework
12/2/2004 1 Drill FW engine mount holes
11/23/2004 1 mark up & drill access firewall holes
9/22/2004 1 interior cabin work
9/20/2004 1 complete riveting aft top section
9/19/2004 2.5 rivet aft top assemly & baggage support assy
9/16/2004 2 fabricate, prime,countersink & rivet rudder cable fairings
9/15/2004 1 fabricate alum brace, drill, dimple, rivet & attach left air scoop
9/14/2004 1.5 fabricate alum brace, drill, dimple, rivet & attach right air scoop
9/10/2004 0.5 attach wire for aileron trim
9/5/2004 0.5 attach brake lines to reservoir
9/1/2004 0.5 sanded panel prior to paint
8/31/2004 1 test prime & paint interior baggage panel
8/29/2004 2 fuel vent assy attach screen, rework ribs for control assy travel
8/28/2004 3 debur, dimple forward cabin top skin, assy vents
8/27/2004 1.5 rivet forward upper cabin to fuselage
8/24/2004 2 install rudder assy, rivet firewall recess panel with proseal
8/23/2004 1 debur, rivet fwd cabin skeleton
8/22/2004 5 attach, drill top forward cabin, debur, attach & rivet brackets
8/21/2004 2.5 fabricate forward cabin bracket, prime, begin installation
8/17/2004 1 run static line
8/16/2004 2 putz around.static line…elevator & vs tips..
8/14/2004 2 fabricate & prime forward cabin parts
8/12/2004 2.5 attach control stick to interior cabin
8/10/2004 2 build elevator & center control levers, mount to bellcrank & control levers
8/9/2004 1.5 debur, dimple forward aft skin
8/8/2004 5 finish connection of fuel vent & brake lines, some fuel lines & setup valve
8/7/2004 6 redo VS to spar as I was unable with setup, Fabricate rudder stops, install rudder…
8/6/2004 1.5 begin setup of VS
8/5/2004 2.5 continue install of VS
8/4/2004 2.5 attach elevators, build & attach elevator control tube
8/3/2004 3.5 drill & attach points for HS, fabricate spacers…, torque down HS
8/2/2004 2 begin setp for HS, drilled horns for push tube
8/1/2004 2 brake lines, fittings, pitot work…
7/31/2004 4 debur, dimple, rivet aft top skin, fuel tube bending & fitting
7/30/2004 0.5 set brake fittings
7/29/2004 3 attached brake lines
7/28/2004 1.5 rivet forward cabin area, review brake setup…
7/28/2004 1.5 complete rudder bracket with litening holes & rivet, drill & attach brake reservoir
7/27/2004 2.5 drill, install, torgue bolts on landing weldments
7/22/2004 2 attach left landing gear weldment
7/21/2004 3 flap actuator installation
7/20/2004 1.5 attach right landing gear weldment
7/19/2004 1.5 attach bolts to harness anchors, debur & dimple bulkheads
7/18/2004 2 removed aft top skins for dimple,debur, fixed gusset plates, installed rudder cables
7/18/2004 5.5 continue flap actuator assy installation
7/17/2004 5 floor panel to Firewall recess panel, flap actuator assy installation…
7/16/2004 3 set nutplates, cleco on forward cabin covers, route rudder cables on inside cabin
7/15/2004 3 completed seat assy
7/14/2004 1 continue building seats
7/13/2004 3 build seat assemblies
7/13/2004 1 build, rivet tunnel assy, attach platenuts to seat bottom panels
7/12/2004 3 rivet aft seat floor panels, fabricate support braces
7/11/2004 5 build seat hinges, drill, rivet, & attach to aft floor
7/10/2004 1.5 attach platenuts on baggage side panels & install in baggage area
7/10/2004 2.5 rivet baggage cover nutplates, notch & install cable wear blocks
7/9/2004 2.5 fit, attach, drill baggage aft support panels
7/8/2004 3 install 6111 top skin frame supports, install, rievt baggage side & floor panels
7/7/2004 2 attach, cleco, drill forward top skin
7/6/2004 2 assemble, drill rivet bellcrank assy, prep & rivet 656 side gussets
7/5/2004 8.5 prep, drill, rivet, side supports, rails, gussettes, bell crank braces…
7/2/2004 4.5 prep & rivet aft deck, fabricate/prep aft deck support braces, fabricate & rivet aft tiedown….
7/1/2004 1.5 level fuselage assy width, length, fore,aft, align aft deck removing twist, drill to longerons
6/30/2004 1 complete lower skin forward to aft riveting, turned the canoe over
6/29/2004 1.5 continue riveting skins, supports…
6/27/2004 4.5 continue riveting skins, supports, baggage floor…
6/26/2004 4.5 rivet lower forward fuselage
6/24/2004 3 rivet left F770 lower side skin with supports, cleco right F770 skin
6/23/2004 5 Continue… debur, dimple,rivet fuselage components, cleco/set left skin
6/22/2004 3 Continue… debur, dimple fuselage side skins
6/16/2004 1 Continue… debur, dimple fuselage side skins
6/15/2004 1 Continue… debur, dimple fuselage assy
6/14/2004 1.5 Rivet center section side supports, countersink center spar bottom flange, join center & aft sections
6/13/2004 6 Continue… debur, dimple, countersink fuselage assy
6/12/2004 1.5 Disassemble fuselage, debur parts
6/11/2004 2.5 Install center section supports, arm rest & baggage section supports & panels, misc final drill all fuselage areas. Remove F770 side skins
6/10/2004 1.5 Fit, Drill F772 Front floor stiffeners
6/10/2004 3.5 Fitted & Completed Rudder & Brake Pedal assy
6/9/2004 1.5 prime, rivet, assy brake pedals. Prep plastic bushing F6115 for brake assy
6/8/2004 5 install F71701 gear plate, F902 support, fabricate & Install F796B,C,D, fabricate & assemble Brake Pedal assy
6/7/2004 3 fabricate, drill, install F684 brackets…
6/6/2004 1 fabricated F717 brackets
6/5/2004 2 fabricate F719B brackets, drill & set F717 & F719 longerons
6/5/2004 2.5 align, set, drill F772 & F770 skins to firewall, drill & cleco firewall bracket to longeron, cutout landing gear leg holes in F770 skin
6/3/2004 0.5 created 904L attach brackets
6/2/2004 4.5 bend & form fit curve F704 front skin to aft skin, drill longerons & skin doublers…
6/1/2004 4 set longerons, attach center fuselage & side skins
5/31/2004 1 adjust longerons for slotted placement in aft cone
5/30/2004 1 prep for center section merge to aft section
5/29/2004 2 drill floor & baggage panels. Drill & attach F715 end seat ribs
5/28/2004 2 correct rib bracket for the control stick insertion, cleco floor panels in seat & baggage section
5/26/2004 2 More prep work & complete riveting on center section
5/25/2004 3.5 Rivet Center section skeleton, bottom skin
5/24/2004 4 Debur, dimple center section, assemble/prepare to rivet skeleton
5/23/2004 3 Debur, flute & dimple center section
5/22/2004 3 Drill center section ribs…
5/21/2004 1 Complete aft section riveting
5/20/2004 3 Cleco center section ribs to bottom skin, drill to size
5/19/2004 3 Begin Center section, fabricate spacers, prep seat & baggage ribs, cleco bulkhead & bottom skin
5/18/2004 4 continue riveting
5/17/2004 6 Prime, rivet aft assy
5/16/2004 6 Drill, debur, dimple aft assy
5/14/2004 3 Cut/Prep J angles, attach/cleco F773 side skins to bulkheads, prepare for drilling
5/11/2004 2 Longerons, start bulkhead to bottm skin assy
5/10/2004 4 Longerons
5/9/2004 2 Longerons prep
5/7/2004 6 finish all bulkheads...
5/6/2004 1 F706, begin assy
5/6/2004 4 F705 build top assy, rivet & complete assy
5/5/2004 4.5 F705 drill, prime, assemble, rivet bottom assy
5/4/2004 1.5 F705 Cut & Fabricate custom parts
5/3/2004 1 F705 Pull parts, mark cuts on alum bar stock
5/3/2004 5.5 F704 rivet & final installation
5/2/2004 1.5 F704 Center section prep
5/1/2004 2 fabricate, build, assemble small sub components for F607 center section
4/30/2004 0.5 pick parts for F607 main section
4/30/2004 3.5 prime, build, rivet FW
4/29/2004 2 prep work, debur, prime
4/28/2004 1 prep work
4/27/2004 0.5 drill fw assy
4/21/2004 0.5 finish drill fw Bracket / floor brace
4/19/2004 2 fabricate & setup Fwf floor bracket
4/18/2004 3 cont fabricate FW parts, build...
4/17/2004 1 fabricate FW partsld...
4/16/2004 1 debur bulkhead parts