Dan's RV7a Builder Website

Panel

Date Session Hours Task
6/2/2006 1 misc panel adjustments
6/1/2006 3 finalize panel & install to cabin, test transmit
5/31/2006 2 more com harness work
5/30/2006 2 more intercom/com work
5/29/2006 3 remove panel & replace intercomm harness
5/28/2006 1 solder headphone & mic on new intercom harness
5/27/2006 2 reattach panel, secure throttle bracket group
5/26/2006 2 reattach panel and modify harnesses
5/21/2006 5 build gps harness, hotwire to panel, mount antenna to fwd dash panel
5/18/2006 1 cut panel hole for the gps airmap2000c
5/17/2006 2 pull panel, mount transponder tray
4/11/2006 1 reset panel & reconnect wiring
11/18/2005 1 drill panel for red panic light for EIS
11/16/2005 1 install EIS 4000 module to panel
11/13/2005 1.5 attach comm wiring harness to intercom & load to panel, prep for panel to cabin install & test
11/12/2005 3.5 complete comm harness & integrate into intercom
11/11/2005 5 build comm harness, prep cabin ribs for comm cable to antenna, fix radio stack for comm
11/10/2005 2 finish building & attach radio stack bracket, remove panel for comm attachment
11/8/2005 3 cutout rear secondary panel for comm radio installation
6/21/2005 1 misc panel, prep & paint panel finish screws…
6/3/2005 1 more panel wiring stuff
6/2/2005 1 grind panel & attach flap panel switch
6/1/2005 1 wire wrapping of intercom harness
5/31/2005 1.5 wire wrapping & wiring behind panel
5/30/2005 2.5 wire intercom & solder plug connections
5/1/2005 2 fabricate remote compass bracket & preliminary intall on F707 bulkhead
4/27/2005 1 mount dynon efis
3/21/2005 1.5 complete db sub solder connections on the intercom assy
3/20/2005 2.5 build intercom & power outlet wiring harnesses
1/29/2005 3 mount power outlets, exp2 bus to support bracket & indicator guage, headphone,mic& stereo toggle switch to panel
1/27/2005 2.5 final coat on panel, wrinkle paint map box, begin setup of panel items
1/26/2005 1 3 coats of wrinkle paint on the instrument panel
1/25/2005 1.5 cut elt & intercom mounting holes in panel, sand & primer.
1/18/2005 0.5 sand down & rework panel surface, test paint wrinkle paint
1/17/2005 2 redo map box door & rivet to panel, locate & drill additional hole for stereo jack input
1/9/2005 2 completed cutting panel
1/1/2005 2 mapbox prep, locate & cut panel for headphones, mic & power plugs
12/30/2004 1 mapbox prep
12/29/2004 1 mapbox prep
12/26/2004 1 continue with panel
12/24/2004 2 panel cutouts
12/23/2004 1 begin panel cutouts
12/6/2004 1 Layup work
12/4/2004 1 map box drill, countersink & rivet
12/1/2004 1 map box drill, debur..
11/30/2004 1 begin panel layout, cut map box hole